Before any sums: the reasons to say no in ten minutes
Many tenders can be ruled out without sums. If any answer is no, let it go:
- Do you meet the criteria: turnover, similar contracts, registrations?
- Will people and equipment be free for the whole contract?
- Can you live with the specification's penalties and response times?
- Can your cash cope with how the buyer really pays? That is a cash flow forecast sum.
On your own case, ask your adviser: this page is not legal advice.
What a losing bid really costs you
A bid costs money even when someone else wins, and few firms count all of it: hours on the documents, site visit, method statement, any bid bond, the owner's time. Count the hours at full cost, not as free. And if you can prepare two bids a month, every tender you pick rules out another. So ask: is this tender worth more than the others in front of me?
The expected value sheet, line by line
Expected value = probability of winning × (margin if you win − cost of delivery risk) − cost of the bid
| Item | Where it comes from | Typical mistake |
|---|---|---|
| Margin if you win | Full cost against the price you plan to bid | Using the buyer's estimated value |
| Delivery risk | Penalties, extra equipment and staff, late payment | Leaving it at zero because “we'll see” |
| Cost of the bid | Hours, site visit, method statement, any bid bond | Counting cash costs and forgetting the hours |
| Probability of winning | Similar tenders already closed, your bid log | Trusting whoever knows the buyer |
How good do your odds need to be?
It's the shakiest number on the sheet, but often you only need to know whether it's above or below the point where the bid pays for itself.
Break-even probability = cost of the bid ÷ (margin if you win − cost of delivery risk)
Where to get a win probability you can trust
Gut-feel probabilities tend to run too high: people remember the wins, and every tender looks special. Start from similar cases and then adjust, as in reference classes:
- similar closed tenders from the same buyer: how many bids, who won (how many bids a tender will get);
- the award criteria: on lowest price your costs decide, when quality is scored your proposal counts too (price scoring formulas);
- who holds the contract now (bidding against the incumbent);
- your own log, for tenders of the same kind.
The bid log: write the probability down before the award
Without a log you'll never know if your probabilities are any good: that is calibration applied to your own tenders. One line per tender is enough, skipped ones included.
Before you submit
Write down the probability, the range and the expected value. After the result, memory edits itself.
At the award
Note who won, at what price, how many bids and where yours placed.
Every few dozen tenders
Compare the odds you gave with your actual wins. Won one in eight of those you rated one in three? Lower your estimates.
What VIDI adds to the decision
VIDI estimates the part of the sheet you can see from outside: how many bids are likely to arrive, with a range, which firms usually turn up, and whether the contract is more likely to go to a small or a mid-sized company. It works from tenders already closed, whose real outcome is in public tender data.
You get a document with the range, what would overturn it, how far to trust it and where it comes from. If you want your own bid log used too, we sign an NDA first (see data and confidentiality). The service is under VIDI Public Tenders; the sample document shows an answer.
Over 3 billion
Over 3 billion data points read from public registers, about 6 million cases for training.
What the sheet won't decide for you
- Margin, bid cost and delivery risk are your figures: VIDI doesn't know your costs.
- The chance of winning one tender is the weakest estimate: VIDI does not beat the best statistical rule by a safe margin, and the document says so.
- It doesn't assess your technical proposal or predict the panel.
- Reasons without a number, such as getting in with a new buyer, stay yours: they don't belong in the probability.