The price weighting doesn't tell you how much price counts
The tender splits the points between quality and price, say 70 and 30. What counts is the gap between the bids' price scores, and the formula creates it: if it keeps everyone near the maximum, thirty price points can shrink to two or three points of real difference, and quality decides. The tender documents say which formula applies: read it there rather than assume it.
European procurement rules ask buyers to award contracts to the most economically advantageous tender. That can be defined by price or cost alone, and each country may limit the use of price as the only criterion.
Four formulas you'll find in tender documents
| Formula | How it awards points | What it does to your discount |
|---|---|---|
| Linear on the largest discount | Your discount divided by the largest one offered, times the maximum points. No discount, zero points. | Every point of discount is worth the same: price weighs a lot. |
| Lowest price divided by yours | The lowest price offered divided by yours, times the maximum points. Even no discount scores well. | Scores stay close: a lower price buys little. |
| With an exponent | The linear one, with the ratio raised to a power below one. | The first points of discount are worth a lot, the last ones little. |
| Two-slope | Up to a threshold set in the tender, such as the mean discount, points rise fast; beyond it, slowly. | Past the threshold a point of discount buys almost nothing. |
Price points = maximum points × (your discount ÷ largest discount among all bids)
Why your points depend on other bidders' prices
Almost all these formulas are relative: your score moves when the other bids move. Under the linear formula, if a rival offers twice your discount, you get half the points.
So read your price score as a range: the largest rival discount sits between a credible low and a credible high, and also depends on how many bids the tender will get. Then simulate: thousands of possible tenders and, for each price you're considering, the probability of coming out ahead.
Is a quality point cheaper than a price point?
A point won through a lower price costs revenue you give up for the whole contract. A quality point costs whatever it takes to earn it: hours, equipment, a dedicated contract manager. Divide the cost of each lever by the points it brings and start with the cheapest, staying above the price your costs can bear (see how low to bid).
Two things to check before you set your discount
- Forgetting the low price check: if a bid looks abnormally low, European rules require the buyer to ask for an explanation and consult the bidder before rejecting it (see abnormally low bids).
- Setting a price before asking whether to bid at all.
This page explains the arithmetic, not the law: how a clause in your tender should be read is a matter for your own adviser.
What VIDI can estimate in a scored tender, and where it stops
VIDI starts from closed tenders similar to yours, with the real outcome read from public tender data, and estimates how many bids to expect and how likely it is that a deep discount will be needed. That is only a starting point for the largest discount you'll face: in a scored tender the biggest discount doesn't always win. The document puts the estimates next to your full cost and says how far to trust each one; with your tender's formula you can then work out how many points each discount you're considering is worth.
Over 3 billion
Over 3 billion data points read from public registers, about 6 million cases for training.
- It doesn't predict the panel's quality scores: you estimate those.
- It doesn't pick your price: the figure is yours.
- With few similar cases the range widens, and the document says so.
A typical answer is in the sample document, and the service is described under VIDI Public Tenders. We sign an NDA before receiving your files (see data and confidentiality).