What does it mean to look at a plan from the outside?
Whoever writes a plan sees it from the inside and, on time, cost and results, tends to err towards optimism: Kahneman and Tversky called it the planning fallacy. The outside view asks instead how it usually went for people who did something similar.
In the 1970s Kahneman was writing a school curriculum with a team, and everyone expected about two years. An expert colleague, asked about similar teams, said about four in ten had never finished and none had taken under seven years. It took eight. He knew those cases, but had not used them for his own project.
Bent Flyvbjerg made this a method for costing large infrastructure projects. The same check applies to the revenue in a business plan for a grant.
Which cases belong in the class, and which stay out?
Similar means the same mechanism, not the same look: a firm in another industry using your technology may teach you more than a competitor doing something else.
- The same decision and a similar size: a three-person project is not judged against thirty-person ones.
- The outcome measured the same way, and chosen in advance: months to full output, final cost against budget.
- The failures too: those who closed or gave up stay in the class.
- A comparable period: after an abrupt change in rules or market, earlier cases count for less.
A narrow class is closer to you but has few cases; a broad one has many but mixes different situations. Build both: if they agree, rely on them; if they diverge, put the gap in the plan.
From the class to your case, without sliding back into optimism
Fix the criteria before seeing the outcomes
Otherwise you keep the cases that agree with you.
Look at the spread
The typical case, how many run far over, how many never get there: the average hides the long tails of delays and overruns.
Write down how you differ
Only with facts: an identical plant already running, a customer already signed. “We are better organised” is what nearly everyone thinks.
Adjust only a little
Move the estimate only as far as evidence like yours has really predicted the outcome in the past.
Estimate = class value + c × (estimate from your case − class value)
Take the range from the class, not from the plan; the guide on probabilistic forecasts explains how to read the resulting probabilities.
Six months to get a new line up to full output?
Mistakes that spoil a reference class
- Counting only those who made it: abandoned projects are rarely written up, and a list of well-known cases has already left them out.
- Classes of three cases, where the range is an impression rather than a measurement.
- The average instead of the spread: a modest average delay can hide cases stuck for a year.
- Counting twice: if the class is made of firms as experienced as yours, that experience is already in its numbers.
Only outcomes show whether the adjustment works: if your adjusted estimates still miss in the same direction, a calibration check will reveal it.
When similar cases are not enough
- Things that are genuinely new: the class is built part by part, as for a product with no history.
- Sudden breaks: after an unprecedented shock, earlier cases describe a world that no longer exists.
- The single case: if four in ten stall, nobody knows in advance whether yours is one of them.
- Outcomes nobody records: then you need company or industry data.
In these cases VIDI has no firmer ground than you for that part, and the document says so by stating how far to trust the answer.
How VIDI uses cases that have already closed
VIDI splits the question into measurable parts and, for each, looks for the most similar closed cases, with the real outcome, whatever it was. It reads them from billions of data points in public registers.
For each question the document shows which similar cases the estimate rests on, what would overturn it and how far to trust it. See the sample document, and Method and measures for how we check whether VIDI was right.