What happens inside a simulation, one run at a time
An ordinary plan uses one number per line: sales, price, costs, days to payment. A Monte Carlo simulation starts from the fact that each could turn out differently. Nicholas Metropolis and Stanislaw Ulam described it in 1949; the name comes from the casino.
Write down the calculation
The formula linking the inputs to the result. If it is wrong, the simulation repeats the mistake thousands of times.
Give uncertain inputs a range
A low, a high and where values tend to cluster. A signed lease stays a single number.
Link the inputs that move together
When sales fall, customers often pay later too. Write the link in, or the simulation ignores it.
Draw, repeat, count
Each run picks a value per input and redoes the sum. Then you count how many runs end in a loss and how many beat the target.
Why a plan built on averages gets even the average wrong
A plan built on averages should surely give the average result. It doesn't, once the calculation contains a cap, a threshold or a penalty.
A department makes at most 1,000 units a month and average demand is 1,000. When demand reaches 1,200 you sell 1,000; when it drops to 800 you sell 800. On average you sell less than the plan. Two parallel jobs, each on time half the time, are both on time only a quarter of the time. A simulation redoes the real calculation on every run and catches this by itself.
Where the ranges you feed in should come from
A simulation creates no information; it reshuffles what you give it. Feed it guesses and the result has the precise look of ten thousand runs and the substance of a hunch. Ranges should be estimated from similar closed cases with the real outcome: reference classes.
Shape matters too. Bent Flyvbjerg showed on large public projects that costs overrun far more often than they underrun, so a range centred on the budget is wrong by design.
| Input | How it behaves | Common mistake |
|---|---|---|
| Days to payment | Lopsided: some customers pay very late | Average with a symmetrical range |
| Costs of a job | Overrun far more often than they underrun | Range centred on the quote |
| Energy and raw materials | When they rise, competitors' prices usually rise too | Raising them while selling prices stand still |
| Sales and cash receipts | When sales fall, payments slow down | Drawing them as independent |
The last mistake is the most expensive. Drawn separately, linked inputs cancel each other out and the range of the result comes out too narrow. It is the opposite of adding up every low case, as the guide on the forecast range explains.
What to read in the results, beyond the average
The average of all runs tells you little. To decide, look at:
- how often a threshold that matters is crossed: cash beyond the overdraft, margin below fixed costs;
- where the middle of the results falls: that is the range, and its ends give the downside and upside scenarios;
- which input drives most of the gap between good and bad runs: that is where better data, a clause or a hedge pay off;
- what changes with another choice, tested on the same runs, so the difference comes from the choice and not from luck.
How VIDI uses simulations, and how it checks them
VIDI breaks the question into measurable parts and estimates each from closed cases with the real outcome, drawn from billions of data points in public registers and from the company's own files. It then simulates how they combine.
A simulation can be quietly wrong even when the calculation is right. So VIDI checks its own numbers against outcomes: what it gave 2 times in 10 should have happened about 2 times in 10. That is calibration.
95 out of 100
When VIDI by EE Partner is 90% sure or more, it's right 95 times out of 100.
The document gives you the range, the scenarios, the reasoning behind the number and the data in Excel: see the sample document. How we compare forecasts with outcomes is in Method and measures.
When simulating adds nothing, or leads you astray
- If the decision hinges on a single uncertain number, its range is enough.
- No run will find a mechanism missing from the calculation, such as a bank cutting your overdraft just as results worsen.
- For an event without precedent there is no honest range: you can simulate what it would do to the accounts, not how likely it is.
- Where there are no similar closed cases to estimate the ranges from, VIDI's result stays uncertain too, and the document says so.
- The worst runs, one in a thousand, depend more on the shape of the ranges than on the data: a warning, not a measurement.
- How much risk you can carry is the company's call, with VIDI or without.