Why is an unsold hour lost for good in a services firm?
A manufacturer can put parts in stock. A firm selling consulting, IT projects, engineering or cleaning can't: an hour when paid staff aren't working for a client never comes back. Capacity is people, and it grows in steps. A new hire costs you for months before they pay their way.
So most hard decisions are really one: how many people to carry against the work that will come in. Then there's cash. Salaries go out every month, invoices are often paid at 60 or 90 days, and a firm that grows fast burns cash just as its profit improves. A month-by-month cash flow forecast shows this in time.
How many of each person's hours do you really sell?
From contracted hours, take off holidays, sickness, training, internal meetings and time on proposals. Then take off hours worked but not billed: overrun fixed-fee jobs, free fixes, end-of-project discounts. The hours left, divided by available hours, give you utilisation.
Break-even utilisation = full cost of the person ÷ (realised rate × available hours)
The figure varies by role: people who lead teams or sell bill less. Compare it with the hours each role billed over the last two years; if you don't record time by project, start there. The calculation by role is in how many people you need.
Hire before signature or after: the sums on a contract that may slip
What is your list of open proposals really worth?
The usual way is to multiply each proposal by a probability set by eye. The total looks precise, but the probabilities are the ones you hope for, and there is no date. When you pay salaries, a contract six months late is almost as bad as none. Measure your own past instead:
- how many proposals from the last two or three years became contracts, by size, type of work, and new or existing client;
- how long passed between the promised signing date and the real one;
- which sectors your clients work in: if most are in manufacturing or construction, their year decides yours, a few months later.
You start from similar cases already closed, the reference class, and then adjust for what you know about today's client. The same groundwork underpins a sales forecast.
Fixed fee or time and materials: where the margin leaks
On fixed-fee work the extra hours are yours. Project estimates nearly always come out short: Kahneman and Tversky called it the planning fallacy, and Flyvbjerg has measured it on large projects of every kind. The same mechanism works on a website or an expert report: whoever estimates pictures how this job will go, not how similar jobs went.
- Put estimated and actual hours side by side for your last closed fixed-fee projects: the average ratio is your correction, and its spread tells you the contingency to add.
- Write down what's included and how extra requests are charged; for existing clients, see raising prices.
What VIDI does with a question from a services firm
“Do we hire two people now?” becomes smaller questions: how much work clients will bring, how many proposals will close and when, what happens to cash in each scenario. For your clients' sectors and their published accounts, VIDI starts from millions of cases already closed, with the real outcome, and billions of data points read from public registers.
We usually need timesheets, invoices and past proposals with outcome and dates; they reach us only after an NDA is signed (how we handle them is under data and confidentiality). The document gives the range, scenarios and how far to trust it, as in the sample document. The service is VIDI Business Decisions.
71.6%
On complex market questions, the path VIDI by EE Partner pointed to worked 71.6% of the time.
What VIDI can't know about your services firm
- It doesn't assess people: it works by role and on aggregate figures, never on the individual.
- It doesn't know what your biggest client is thinking. If they are a third of your turnover, the scenarios can show the sums with them and without them; the relationship is yours to judge.
- For a new service, with no past proposals and no similar firms, the estimate has little to start from, so the range is wide and the document says how wide.