What do you count first: people or work?
The work that is coming, not the organisation chart. For each role, pick what drives it (units to assemble, order lines, accounts to manage, invoices) and estimate how many hours it will take over the coming months.
People needed (full-time equivalent) = expected hours of work in the role ÷ productive hours of one person per year
Two people on half hours count as one. If the work bunches into a few months, size the role for the peak, not the yearly average. The volume estimate is the most uncertain part, and it is the same as your sales forecast.
Why roles don't all grow with revenue
| Role | What drives it | How it grows |
|---|---|---|
| Production, warehouse, customer service | Units, order lines, calls | Roughly in line with volume |
| Sales | Accounts and new markets | Ahead of revenue, which arrives months later |
| Finance, purchasing, payroll | Documents, suppliers, payslips | In steps, often absorbed by better processes |
| Team leaders | People to coordinate | In jumps, when a team gets too big to run |
Doubling revenue does not double headcount. One company-wide number hides the teams that will be short and those with people to spare.
How many of today's people will still be here in a year?
Take today's headcount by role and subtract known retirements, expected leavers, internal moves and long absences. Leavers are estimated for the role, never for the person: how many people left it in recent years, out of how many there were. You don't need to know who will go.
People to find = people needed − people available on that date
Train, hire, redeploy or wait: how to choose
| Option | When it makes sense | What it really costs |
|---|---|---|
| Develop your own people | Skills close to ones you already have | Training, time off the job, the vacancy it leaves |
| Hire from outside | Skills missing altogether, or a lasting need | Full cost, recruitment, months before they are up to speed |
| Redeploy from another role | One team has spare capacity, another is short | The learning curve and the risk of leaving the other team short |
| Wait and cover | Uncertain or seasonal need | Overtime or agency staff: dearer by the hour, but easy to stop |
Start date = date the person must be productive − time to hire − time to train
The lead time hits your cash flow: you pay the person from day one, while the work that justifies the hire comes later. Use the full cost, with employer contributions, pension costs, recruitment and training, not just the gross salary.
Mistakes that throw a workforce plan off
- Counting heads instead of hours.
- Treating contract hours as productive: the team looks balanced until holidays and absence hit.
- Asking team leaders how many people they want: those under pressure ask for more, those afraid of losing influence ask for fewer.
- Hiring for the best case and being left with fixed costs that don't come down.
An assembly team under three order scenarios
What VIDI adds to the sum
The sum is simple; its inputs are not. In workforce planning VIDI estimates the uncertain parts: the workload for each role, with its range and scenarios; expected leavers, from your history and similar companies; how hard a profile is to find and how long it takes, from public labour market data; the cost of each option.
We need your goals with a number, headcount by role from a payroll export, and the skills each role needs. An NDA is signed before we receive any files (data and confidentiality). You receive a document with, for each role, the number, the scenarios, the option with cost and timing, and how far to trust it; the steps are in how we work. The decision stays yours.
Where VIDI won't help you on staffing
- It won't tell you who will leave or who performs better: it works by role and on aggregate numbers, by design.
- In roles held by one or two people, averages say little: the choice depends on who is there, and you know that better.
- A role your company has never had has no history, so the range stays wide.
- Morale, the quality of managers and union agreements affect leavers and timing, but they are not in the data.